Serbia: Morava Corridor Motorway-01
Case Tracker
Complaint Overview
Community member
Environmental issues; Health and safety; Loss of value for land; Loss of development rights
Project Information
MIGA guarantee for EUR 411.4 million (c.US$ 451.8 million).
Synopsis
The Morava Corridor Motorway Project consists of a greenfield 112 km dual-carriageway tolled motorway, within a 900 meter right of way, located approximately 200 km south of Belgrade, in a low-level flood plain running east/west along the West Morava River Valley. The Project includes (i) above-ground structures such as interchanges, bridges, culverts, and over/underpasses; (ii) a telecommunication network (digital corridor) supported by power lines and communication cables to connect the telecom stations within the motorway (at rest areas, parking lots, and near traffic loops) and to manage traffic through various traffic control, surveillance, and tolling systems; and (iii) river regulation works intended to protect the Project and its surrounding areas from flooding.
The complaint raised concerns relating to economic displacement, health and safety, environmental issues, and violations of laws and standards in relation to the construction of the Morava Motorway.
In October 2023, CAO found the complaint eligible and conducted an assessment. Prior to and during CAO's assessment, the complainant, the project implementer, and MIGA continuously worked towards finding a resolution to the complainant’s concerns. These efforts led to the resolution of the complainant’s request for full expropriation of his property, subsequently resolving the complaint issues related to economic displacement, health and safety, and environmental impacts. However, the complainant continued to express concerns about the expropriation process and the compensation offer he received, particularly their alignment with MIGA’s environmental and social performance standards.
The parties expressed no interest in engaging in a CAO-facilitated dialogue to resolve these remaining issues. Consequently, in accordance with CAO policy, the case was transferred to CAO’s Compliance function for appraisal.
The case is currently under compliance appraisal.
Status as of March 04, 2024.